Commissioning

10.4.3 To perform a test run

10.4.4 To perform an actuator test run

10.4.5 Underfloor heating screed dryout

Installer reference guide
158
Prerequisite: Make sure that the leaving water temperature home page, room
temperature home page, and domestic hot water home page are turned OFF.
1 Set the user permission level to Installer. See
4
to
Installer" [
 109].
2 Go to [A.7.1]:
> Installer settings > Commissioning > Test run.
3 Select a test and press
4 Select OK and press
Result: The test run starts. It stops automatically when done (±30 min). To stop it
manually, press
, select OK and press
INFORMATION
If 2 user interfaces are present, you can start a test run from both user interfaces.
The user interface used to start the test run displays a status screen.
The other user interface displays a "busy" screen. You cannot use the user
interface as long as the "busy" screen is shown.
Perform an actuator test run to confirm the operation of the different actuators.
For example, when you select Pump, a test run of the pump will start.
Purpose of the actuator test run is to confirm the operation of the different
actuators (e.g., when you select pump operation, a test run of the pump will start).
Prerequisite: Make sure that the leaving water temperature home page, room
temperature home page, and domestic hot water home page are turned OFF.
1 Set the user permission level to Installer. See
4
to
Installer" [
 109].
2 Go to [A.7.4]:
> Installer settings > Commissioning > Actuator
test run.
3 Select an actuator and press
4 Select OK and press
Result: The actuator test run starts. It automatically stops when finished. To stop it
manually, press
, select OK and press
The underfloor heating (UFH) screed dryout function is used for drying out the
screed of an underfloor heating system during the construction of the building.
The UFH screed dryout function can be executed without finishing the outdoor
installation. In this case, the backup heater will perform the screed dryout and
supply the leaving water without heat pump operation.
If the outdoor unit is not yet installed, connect the main power supply cable to the
indoor unit via X2M/30 and X2M/31. See
4
supply" [
 93].
. Example: Heating.
.
.
. Example: Pump.
.
.
"8.3.1  To connect the main power
"To set the user permission level
"To set the user permission level
ERLA03DAV3 + EHFH03S18DJ3V
Daikin Altherma 3 R F
4P596806-1 – 2019.10
Table of Contents
loading

Table of Contents