Installation Procedures - Emerson Rosemount 2051 Reference Manual

Pressure transmitter with hart revision 5 and 7 selectable protocol
Hide thumbs Also See for Rosemount 2051:
Table of Contents
Hardware installation
February 2024
3.2.3 
Mechanical considerations
Steam service
NOTICE
For steam service or for applications with process temperatures greater than the limits
of the transmitter, do not blow down impulse piping through the transmitter.
Flush lines with the blocking valves closed and refill lines with water before resuming
measurement.
Side mounted
When the transmitter is mounted on its side, position the Coplanar
proper venting or draining.
Keep drain/vent connections on the bottom for gas service and on the top for liquid
service.
Related information
Mounting requirements
3.3 

Installation procedures

3.3.1 
Mounting the transmitter
Mount process flanges
Procedure
Mount the process flanges with sufficient clearance for process connections.
 CAUTION
For safety reasons, place the drain/vent valves so the process fluid is directed away from
possible human contact when the vents are used.
In addition, consider the need for a testing or calibration input.
NOTICE
Most transmitters are calibrated in the horizontal position. Mounting the transmitter in any
other position will shift the zero point to the equivalent amount of liquid head pressure
caused by the varied mounting position.
Related information
Trimming the pressure signal
36
Reference Manual
00809-0100-4107
flange to ensure
Rosemount 2051
Table of Contents
loading

This manual is also suitable for:

Rosemount 2051c