5. Connection and Operation

The system may be installed and wired only by qualified electricians in
accordance with applicable safety regulations
When installing the electrical wiring, please note the nominal amperage of
your incoming feeder
1)
Inspection:
Inspect the packaging carton and its contents for damage. Please inform the transport agency
immediately should you find signs of damage. Please keep the packaging in a safe place for future use.
Note: Please ensure that the incoming feeder is isolated and secured to prevent it from being
switched back on again.
2)
Connection:
2.1) UPS Input Connection
If the UPS is connected via the power cord, please use a proper socket with protection against
electric current, and pay attention to the capacity of the socket: over 10A for 1KVA & over 16A for
2KVA & 3KVA.
2.2) UPS Output Connection
The output of the UPS is CE socket-types only. If the load is couple of PCs simply plug the load
power cord to the output sockets to complete connection. However, if there are more loads, cut the
load end of the load power cord and wire to the extension board. Use one cord for every 5A load.
Model No.
GXT1000-MT / GXT1000L-MT
GXT2000-MT / GXT2000L-MT
GXT3000-MT / GXT3000L-MT
Page 10
Output Socket (pcs)
4(CE)
6 / 4(CE)
4(CE)
V2.11
Installation and User Manual
Connection and Operation
Terminal Block
Nil
Nil /Available
Available
Emerson Network Power
Table of Contents
loading

Table of Contents