Summary of Contents for Fujitsu SPARC Enterprise T5120
Page 3
SPARC Enterprise T5120 and T5220 Servers Site Planning Guide Manual Code C120-H027-03EN Part No. 875-4190-12 July 2009, Revision A...
Page 4
Fujitsu Limited or Sun Microsystems, Inc., or any affiliate of either of them.
Page 5
Aucune partie de ce produit, de ces technologies ou de ce document ne peut être reproduite sous quelque forme que ce soit, par quelque moyen que ce soit, sans l’autorisation écrite préalable de Fujitsu Limited et de Sun Microsystems, Inc., et de leurs éventuels bailleurs de licence.
Read this manual thoroughly. Use the product according to the instructions and information available in this manual. Keep this manual handy for further reference. Fujitsu makes every effort to prevent users and bystanders from being injured or from suffering damage to their property. Use the product according to this manual.
T5220 Servers Overview Guide SPARC Enterprise T5120 and T5220 Servers Installation Guide viii SPARC Enterprise T5120 and T5220 Servers Site Planning Guide • July 2009 Description Minimum steps to power on and boot the server for the first time Minimum steps to power on and boot the...
Page 11
Title SPARC Enterprise T5120 and T5220 Servers Service Manual SPARC Enterprise T5120 and T5220 Servers Administration Guide Integrated Lights Out Manager 2.0 User’s Guide Integrated Lights Out Manager 2.0 Supplement for SPARC Enterprise T5120 and T5220 Servers Integrated Lights Out Manager (ILOM) 3.0 Concepts Guide...
Page 12
URL. For Users in U.S.A., Canada, and Mexico: (https://download.computers.us.fujitsu.com/) For Users in Other Countries: (http://www.fujitsu.com/global/contact/computing/sparce_index.ht SPARC Enterprise T5120 and T5220 Servers Site Planning Guide • July 2009...
“Ambient Relative Humidity” on page 10 ■ “Airflow Considerations” on page 11 ■ For safety and compliance information, refer to the SPARC Enterprise T5120 and T5220 Servers Safety and Compliance Guide and the documentation that came with your server. Related Information “Physical Specifications”...
Height (2 rack units) Weight, approximate (without PCI cards and rackmounts) Related Information “Minimum Clearance for Service Access” on page 3 ■ SPARC Enterprise T5120 and T5220 Servers Site Planning Guide • July 2009 U.S. Metric 16.75 in. 425 mm 28.125 in.
Minimum Clearances Needed for Service for Both Servers TABLE 3 Description Clearance, front of system Clearance, rear of system Related Information “Environmental Specifications” on page 4 ■ SPARC Enterprise T5120 and T5220 Servers Site Planning Guide Clearance 36 in. (91 cm) 36 in. (91 cm)
Shock Related Information “Power Source Requirements” on page 5 ■ SPARC Enterprise T5120 and T5220 Servers Site Planning Guide • July 2009 Operating • Sea level to 2953 ft (900m): 41°F to 95°F (5°C to 35°C) • Above 2953 ft (900m): Decrease the maximum allowable temperature by 1.6°F/1000 ft...
Server models that run on DC input power require that you build power cables and connect to DC input power as specified in the SPARC Enterprise T5120 and T5220 Server Installation Guide. Use the specifications only as a planning guide. For more precise power values, make power measurements on your specific server configuration using your planned workload.
Page 18
Maximum operating input current Maximum operating input power Maximum heat dissipation Maximum standby power SPARC Enterprise T5120 and T5220 Servers Site Planning Guide • July 2009 AC Input Models DC Input Models 100 to 240 VAC, -48 to -60 VDC 50-60 Hz At 100 VAC: 7.3A...
Page 19
Under Nominal Temperature and Voltage Conditions (4 core, 1.2 GHz processor, with four 1 GB FBDIMMs, no HDDs, no PCIe I/O cards) Idle input power Peak input power running SpecJBB SPARC Enterprise T5120 and T5220 Servers Site Planning Guide 471.5 W 440.4 W 807.4 W 754.1 W...
“Acoustic Noise Emissions” on page 8 ■ Acoustic Noise Emissions Declared noise emissions for both the SPARC Enterprise T5120 and T5220 servers are in accordance with ISO 9296 standards. Acoustic Noise Emissions for the SPARC Enterprise T5120 Server TABLE 9...
Agency Compliance Specifications Refer to the SPARC Enterprise T5120 and T5220 Servers Safety and Compliance Guide for a full list of agency compliance specifications. Related Information “Operating Environment Requirements” on page 9 ■ Operating Environment Requirements The operating environment requirements are the same for both the SPARC Enterprise T5120 and T5220 servers.
Electrostatic discharge (ESD) is easily generated and less easily dissipated in areas where the relative humidity is below 35%, and becomes critical when levels drop below 30%. SPARC Enterprise T5120 and T5220 Servers Site Planning Guide • July 2009...
Airflow Considerations Ensure unobstructed airflow through the chassis. ■ Ensure that inlet air enters at the front of the server and exits from the back. ■ Ensure that the server ventilation openings used for intake and outflow of air ■...