The Auxiliary Overload Device (AOD) is an add-on device for the S-60 Crossing Gate, with a Rev C or Older Main Board installed. The AOD is designed to detect an entrance gate motor stall based on the supply voltage and amount of time the S-60 actively drives the gate motor. The AOD, upon detection of a stall condition, will engage a relay, interrupting the supply of power to the motor and have the gate arm descend in a controlled manner. The AOD is powered by the S-60 drive mechanisms and is not capable of introducing foreign energy or otherwise interfering with the S-60 safety related motor drive in a manner that would cause an unsafe condition. Refer to the S-60 Crossing Manual for further information. (Siemens Doc. No.: 074050).


THIS PROCEDURE WILL REQUIRE TEMPORARY OPENING
AND CLOSING OF HIGHWAY CROSSING WARNING DEVICE CIRCUITS. PRIOR TO PERFORMING, TAKE THE NECESSARY PRECAUTIONS TO WARN PEDESTRIANS, PERSONNEL, TRAINS, AND VEHICLES IN THE AREA UNTIL PROPER OPERATION IS RESTORED AND VERIFIED.

Prepare Crossing

Prepare the crossing for installation. Open the Gold-Nut, which will lower the Gate Arm. See S-60 Crossing Gate Manual (Siemens Document Number 074050) for further information.
Prepare Crossing

NOTE
Visually inspect the gate mechanism to ensure there are no cams and/or wires attached to terminals T11 top and bottom and T12 top and bottom.
Inspect the gate mechanism
Gate Mechanism Visual Inspection


IT IS NECESSARY TO FOLLOW THIS PROCEDURE AND ENSURE WIRES ARE INSTALLED IN THE PROPER LOCATIONS FOR THE GATE MECHANISM TO OPERATE PROPERLY.

Wiring Overview

The following is an overview of the AOD wiring:
Wiring Overview

Hardware Installation Overview

The following is the hardware sequence for the AOD installation.
Hardware Installation Overview

Installation Procedure

  1. Remove motor wires from P4 on Main Board
    Installation Procedure - Step 1
  2. Install Ring Terminals on Motor wires.
    Installation Procedure - Step 2
  3. Install AOD Board on AAR Terminals (#11 and #12). Mount the AOD Board with "INSTALL THIS SIDE OUT" facing front as shown below.
    Installation Procedure - Step 3
  4. Install the wiring using the following procedure:
    Installation Procedure - Step 4

Testing Installation

  1. Close the Gold-Nut. Cycle the Gate a minimum of 2 times to verify gate is operating properly. The AOD Board "ON" LED (Green) will illuminate with each motor operation. Note the Red "ACTIVE" LED will illuminate for 3 minutes in the event of a low supply voltage, causing the motor to be in a stall condition.
    Testing Installation

Contact Siemens Customer Service with any questions.

Siemens Rail Automation Corp.
2400 Nelson Miller Parkway
Louisville, Kentucky 40223
California R&D
9568 Archibald Ave., Suite 100 Cucamonga, California 91730
1-800-793-SAFE (7233)

Documents / Resources

Download manual

Here you can download full pdf version of manual, it may contain additional safety instructions, warranty information, FCC rules, etc.

Table of Contents