To perform a test run

Prerequisite: Make sure that the leaving water temperature home
page, room temperature home page, and domestic hot water home
page are turned OFF.
1 Set the user permission level to Installer. See
Installer" [ 4  17].
permission level to
2 Go to [A.7.1]:
> Installer settings > Commissioning >
Test run.
3 Select a test and press
. Example: Heating.
4 Select OK and press
.
Result: The test run starts. It stops automatically when done
(±30 min). To stop it manually, press
INFORMATION
If 2 user interfaces are present, you can start a test run
from both user interfaces.
▪ The user interface used to start the test run displays a
status screen.
▪ The other user interface displays a "busy" screen. You
cannot use the user interface as long as the "busy"
screen is shown.
7.2.4

To perform an actuator test run

Perform an actuator test run to confirm the operation of the different
actuators. For example, when you select Pump, a test run of the
pump will start.
Prerequisite: Make sure that the leaving water temperature home
page, room temperature home page, and domestic hot water home
page are turned OFF.
1 Set the user permission level to Installer. See
Installer" [ 4  17].
permission level to
2 Go to [A.7.4]:
> Installer settings > Commissioning >
Actuator test run.
3 Select an actuator and press
4 Select OK and press
.
Result: The actuator test run starts. It automatically stops when
finished. To stop it manually, press
Possible actuator test runs
▪ Backup heater (step 1) test
▪ Pump test
INFORMATION
Make sure that all air is purged before executing the test
run. Also avoid disturbances in the water circuit during the
test run.
▪ Solar pump test
▪ Shut-off valve test
▪ 3-way valve test
▪ Bivalent signal test
▪ Alarm output test
▪ H/C signal (heating/cooling signal) test
▪ Quick heatup test
▪ DHW pump test
EHFH03S18DJ3V
Daikin Altherma 3 R F
4P596803-1 – 2019.10
.
"To set the user
, select OK and press
.
"To set the user
. Example: Pump.
, select OK and press
.

8 Hand-over to the user

7.2.5
To perform an underfloor heating screed
dryout
Prerequisite: Make sure there is only 1 user interface connected to
your system to perform an underfloor heating screed dryout.
Prerequisite: Make sure that the leaving water temperature home
page, room temperature home page, and domestic hot water home
page are turned OFF.
1 Go to [A.7.2]:
> Installer settings > Commissioning >
UFH screed dryout.
2 Set a dryout program.
3 Select Start dryout and press
4 Select OK and press
.
Result: The underfloor heating screed dryout starts. It stops
automatically when done. To stop it manually, press
and press
.
NOTICE
To perform an underfloor heating screed dryout, room frost
protection needs to be disabled ([2‑06]=0). By default, it is
enabled ([2‑06]=1). However, due to the "installer-on-site"
mode (see "Commissioning"), room frost protection will be
automatically disabled for 36 hours after the first power-on.
If the screed dryout still needs to be performed after the
first 36 hours of power-on, manually disable room frost
protection by setting [2‑06] to "0", and KEEP it disabled
until the screed dryout has finished. Ignoring this notice will
result in cracking of the screed.
NOTICE
For the underfloor heating screed dryout to be able to start,
make sure the following settings are met:
▪ [4‑00]=1
▪ [C‑02]=0
▪ [D‑01]=0
▪ [4‑08]=0
▪ [4‑01]≠1
8
Hand-over to the user
Once the test run is finished and the unit operates properly, please
make sure the following is clear for the user:
▪ Fill in the installer setting table (in the operation manual) with the
actual settings.
▪ Make sure that the user has the printed documentation and ask
him/her to keep it for future reference. Inform the user that he can
find the complete documentation at the URL mentioned earlier in
this manual.
▪ Explain the user how to properly operate the system and what to
do in case of problems.
▪ Show the user what to do for the maintenance of the unit.
▪ Explain the user about energy saving tips as described in the
operation manual.
.
, select OK