Finishing The Outdoor Unit Installation; To Finish The Outdoor Unit Installation - Daikin ERGA06EAV3H Installer's Reference Manual

Hide thumbs Also See for ERGA06EAV3H:
Table of Contents

10 Finishing the outdoor unit installation

10.1 To finish the outdoor unit installation

ERGA04~08EAV3+V3A+V37 + EHSH/X(B)04+08P30+50EF
Daikin Altherma 3 R ECH₂O
4P678716-1 – 2022.01
NOTICE
It is recommended that the refrigerant piping between indoor and outdoor unit is
installed in a ducting or the refrigerant piping is wrapped with finishing tape.
1 Insulate and fix the refrigerant piping and cables as follows:
d
c
a
b
g
a Gas pipe
b Gas pipe insulation
c Interconnection cable
d Field wiring (if applicable)
e Liquid pipe
f Liquid pipe insulation
g Finishing tape
2 Install the service cover.
10
Finishing the outdoor unit installation
|
e
f
Installer reference guide
145