Checklist During Commissioning; Minimum Flow Rate - Daikin Altherma F Installer's Reference Manual

Table of Contents

11.4 Checklist during commissioning

11.4.1 Minimum flow rate

EPRA14~18DAV3+W1 + ETVH16SU18+23EA6V
Daikin Altherma 3 H HT F
4P644738-1 – 2021.02
There is NO water leak inside the indoor unit.
The shut-off valves are properly installed and fully open.
The automatic air purge valves are open.
The pressure relief valve purges water when opened. Clean water MUST come out.
The minimum water volume is guaranteed in all conditions. See "To check the water
volume and flow rate" in
The domestic hot water tank is filled completely.
The minimum flow rate during backup heater/defrost operation is guaranteed in all
conditions. See "To check the water volume and flow rate" in
4
piping" [
 83].
To perform an air purge.
To perform a test run.
To perform an actuator test run.
Underfloor screed dryout function
The underfloor screed dryout function is started (if necessary).
Purpose
For a correct operating unit, it is important to check if the minimum flow rate is
reached. If needed, modify the bypass valve setting.
Minimum required flow rate
25 l/min
To check the minimum flow rate
1 Check the hydraulic configuration to find out which space
heating loops can be closed by mechanical, electronic, or other
valves.
2 Close all space heating loops that can be closed.
3 Start the pump test run (see
4 Read out the flow rate
reach the minimum required flow rate + 2 l/min.
(a)
During pump test run, the unit can operate below the minimum required flow rate.
"8.1 Preparing water
piping" [
"11.4.4 Actuator test
(a)
and modify the bypass valve setting to
11
Commissioning
|
4
 83].
"8.1  Preparing water
4
run" [
 230]).
Installer reference guide
227