Pre-Commissioning Process

Perform the necessarry steps to complete the pre-commissioning process:
1. The customer must review the pre-Commissioning Checklist
Requirement and prepare the VFD for the commisioning procedure.
2. Ensure the Pre-Commissioning checklist procedure is complete prior to arrival of Qualified
Siemens Personnel for commisioning of the VFD.
Note
The VFD must be commissioned by Qualified Siemens Personnel only.
Air Cooled 6SR5