Huawei SmartACU2000B Quick Manual

Huawei SmartACU2000B Quick Manual

Smart array controller with no pid module, 800 v ac
Hide thumbs Also See for SmartACU2000B:
SmartACU2000B Smart Array Controller
Quick Guide (with no PID
Module, 800 V AC)
Issue: 05
Part Number: 31509274
Date: 2017-10-30
HUAWEI TECHNOLOGIES CO., LTD.
Table of Contents
loading

Summary of Contents for Huawei SmartACU2000B

  • Page 1 SmartACU2000B Smart Array Controller Quick Guide (with no PID Module, 800 V AC) Issue: 05 Part Number: 31509274 Date: 2017-10-30 HUAWEI TECHNOLOGIES CO., LTD.
  • Page 2: Product Overview

    6. When installing the device and connecting cables, use appropriate tools and take necessary protective measures to avoid damaging the device. 7. Huawei shall not be liable for any consequence caused by violation of the storage, installation, and operation regulations specified in this document and the user manual.
  • Page 3 Cabinet Dimensions Port Description (1) Protective earthing (PE) cable (2) Waterproof connectors for the RS485 waterproof connector (PE, 3/4 in.) communications cable, network cable, and DC input and output power cables (RS485/ETH/DC, 3/4 in.) (3) DO/AO signal cable waterproof (4) DI signal cable waterproof connector (DI, 3/4 in.) connector (DO/AO, 5/4 in.) (5) Waterproof connector for the single- (6) AI signal cable waterproof connector (AI, 5/4 in.)
  • Page 4 Component 1 of the SmartACU2000B-D-2PLC is the power adapter. This model does not  include components 2 and 14. Component 1 of the SmartACU2000B-D-PLC-24V is the 24 V DC power module. This model  does not include components 5, 6, and 12.
  • Page 5 Configurations in Typical Scenarios Fiber Ring Network (no 24 V DC Input or Output) Connections inside a RS485 communications smart array controller terminal Power Fiber adapter adapter PE bar switch Three- Three- Single- phase input phase input phase input switch 2 switch 1 switch Connections...
  • Page 6 Fiber Ring Network (with 24 V DC Input and Output) Connections inside a RS485 communications smart array controller terminal 24 V DC power Fiber module adapter switch PE bar 24 V 24 V DC output input switch switch Three- Three- Single- phase phase...
  • Page 7 UT-H605 or ES1000 Low-speed Fitting optical FTLF1323P1BTR-HW Can be Smart array bag for module purchased controller optical from Huawei PLCLC5S-ST3P302-HW, LC-LC- ring Optical S2-L2, 3ECA1031LCLC002-01-F, switching jumper or LP-LP-2S-P-SM-002 Miniature circuit Recommended rated current: 32 A; breaker (MCB) number of poles: 2 When the rated AC voltage on ...
  • Page 8 The following table describes the cables to be prepared by yourself in the fiber ring networking scenario. Cross-sectional Area No. Cable Recommended Model or Specifications Range of the Cable (Recommended) Three-core (L1, L2, and L3) outdoor copper  armored cable with three OT-M6 terminals (L1, L2, and L3) When the rated AC voltage on the low-voltage ...
  • Page 9 4G LTE Network (no 24 V DC Input or Output) Connections inside a RS485 communications smart array controller terminal Power adapter module PE bar switch Three- Three- Single- phase phase phase input input input switch 2 switch 1 switch Connections inside a box-type transformer...
  • Page 10 4G LTE Network (with 24 V DC Input and Output) Connections inside a RS485 communications smart array controller terminal 24 V DC power module module switch PE bar 24 V DC 24 V DC output input switch switch Single- Three- Three- phase phase...
  • Page 11 Fitting bags module for the POE Can be Outside the module and purchased smart array customer- from Huawei controller premises and box- equipment type (CPE) transformer Recommended rated current: 32 A; number of poles: 2 When the rated AC voltage on ...
  • Page 12  Network cable A 20 m (65.62 ft) long network cable delivered with from the POE Huawei CPE (If the length is insufficient, prepare a module to the cable with the same specifications as a peripheral network cable.) Common connection: one two-core outdoor ...
  • Page 13: Installing The Cabinet

    Installing the Cabinet Preparations Installation Space Marking-off Template Expansion Bolt The marking-off template and expansion bolts are delivered with the cabinet. (1) Expansion sleeve (2) Flat washer (3) Spring washer (4) M12x60 bolt Securing the Cabinet Wall-mounted Installation DANGER Avoid drilling holes in the water pipes and power cables buried in the wall. ...
  • Page 14 1. Determine the hole positions based on the marking-off template, and then mark the hole positions using a marker. 2. Install expansion bolts. 3. Secure the cabinet. Support-mounted Installation 1. Determine the hole positions based on the marking-off template, and then mark the hole positions using a marker.
  • Page 15: Opening The Cabinet Door

    1. Secure the pole mounting bracket. 2. Secure the cabinet. For details, see "Support-mounted Installation." Opening the Cabinet Door  Before opening the cabinet door, turn off all upstream switches for the smart array controller to power off the smart array controller. If you have to operate an energized smart array controller, wear insulation gloves and take preventive measures.
  • Page 16: Connecting Cables

    Installing the POE Module 1. Loosen screws and remove the mounting board. Do not remove the screws. 2. Remove screws from the POE module installation position. 3. Secure the POE module. (The indicators should be in the lower left corner.) 4.
  • Page 17 Selecting a Connection Method You can connect a peripheral cable to the smart array controller in common mode or through a tube based on site requirements. To prevent poor cable connection due to overstress caused by ground subsidence, it is ...
  • Page 18 1. Remove the locking cap and plug from the waterproof connector, and then remove the waterproof connector. 2. Secure the tube fitting using the nut delivered with the tube. 3. Route the cable through the tube conduit and then fitting. 4.
  • Page 19 Connecting the PE Cable 1. Crimp an OT terminal. 2. Secure the PE cable. Connect the PE cable to the nearest  ground point or the ground bar in the box- type transformer. To enhance the corrosion resistance of a ...
  • Page 20 NOTICE Connect two optical cables in a ring optical network, and connect one optical cable in a star  optical network. As optical cables are hard, prepare optical cables before routing them into the cabinet.  Only professionals are allowed to connect optical cables. ...
  • Page 21 Connecting the Three-Phase AC Power Cable (a Circuit Breaker as the Three-Phase Input Switch) For the smart array controller that supports the access of one PLC route, connect the three-  phase AC power cable to the QF02 switch.  For the smart array controller that supports the access of two PLC routes, connect the first route of three-phase AC power cable to the QF02 switch, and the second route of three-phase AC power cable to the QF04 switch.
  • Page 22 Connecting the Three-Phase AC Power Cable (a Knife Fuse Switch as the Three-Phase Input Switch) For the smart array controller that supports the access of one PLC route, connect the three-phase AC power cable to the FU01 switch. 1. Prepare a cable. 2.
  • Page 23 Connecting the Peripheral RS485 Communications Cable Connect peripheral RS485 communications cables to JX01. All RS485 communications cables are connected in the same way. This section describes how to connect two RS485 communications cables. Port on the JX01 Terminal Block Definition RS485-5 (+) RS485A, RS485 differential signal+ RS485-5 (–)
  • Page 24 6.10 Connecting the LAN Switch Cable 1. Connect the FE1 port on the LAN switch to the ETH1 port on the SmartLogger using the network cable delivered with the LAN switch. 2. Connect the factory- installed power cable to the LAN switch using the wiring terminal delivered with the LAN switch.
  • Page 25 6.12 Connecting the 24 V DC Output Power Cable You can connect one or two 24 V DC output power cables to the smart array controller that supports 24 V DC input and output. DC output power cables are connected in the same manner. This section describes how to connect one route of DC output power cable.
  • Page 26: Verifying The Installation

    6.14 Connecting the Single-Phase AC Power Cable 1. Prepare a cable. 2. Connect the cable to the single-phase input switch. Connect the L and N (L) cables to the L and N (L) terminals of the station-service power source for the box-type transformer through an MCB.
  • Page 27: Powering On The System

    Powering On the System Put on insulation gloves before powering on the system. Ensure that the power voltage of the smart array controller is within the operating voltage range, and the three-phase input voltage is within the PLC module operating voltage range. 1.
  • Page 28 Closing the Cabinet Door 1. Install the support bar. 2. Close the cabinet door and tighten the screws. If the screws used for securing the cabinet door are lost, use the security torx screws in the fitting bag. 10.1 How Should I Power Off the System Before Maintenance? DANGER Put on insulation gloves before powering off the system.
  • Page 29 Apple Store Google Play Huawei App Store Scan here for more documents: Support WeChat You can also log in to Huawei technical support website: http://support.huawei.com Huawei Technologies Co., Ltd. Huawei Industrial Base, Bantian, Longgang Shenzhen 518129 People's Republic of China www.huawei.com...